Capital Outturn Report for 2019/20
Decision Maker: District Executive
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
RESOLVED: |
That District Executive agreed to:- |
|
|
a. |
note the content of the report including the total spend of £65.482m on capital schemes during 2019/20; and small variance of £13k underspent across 57 completed schemes;
|
|
b. |
approve the revised Capital Programme spend as detailed in paragraph 10.
|
Reason: |
To inform Members of the outturn of the capital programme of the Council for 2019/20. |
Publication date: 06/08/2020
Date of decision: 06/08/2020
Decided at meeting: 06/08/2020 - District Executive