Notification of an Urgent Executive Decision - Huish Episcopi Academy Swimming Pool Project
Decision Maker: District Executive
Decision status: Information Only
Is Key decision?: No
Is subject to call in?: No
Decision:
NOTIFICATION: |
That the District Executive noted the urgent decision taken by the Chief Executive, in consultation with the Leader of Council, according to the provision of Section 3-47 (4) of the Constitution, to agree to a revised contribution of £117,094 of S106 receipts to support the Huish Episcopi Academy Swimming Pool Project overall scheme cost of £1,215,116. |
Reason: |
To note the urgent decision taken by the Chief Executive, in consultation with the Leader of Council,to support the Huish Episcopi Academy Swimming Pool Project. |
Publication date: 03/08/2017
Date of decision: 03/08/2017
Decided at meeting: 03/08/2017 - District Executive