Issue - decisions
2018/19 Capital Budget Monitoring Report for the Period Ending 31st December 2018
07/02/2019 - 2018/19 Capital Budget Monitoring Report for the Period Ending 31st December 2018
RESOLVED: |
That District Executive agreed to:- |
|
|
a. |
note the content of the report;
|
|
b. |
approve the revised Capital Programme spend profile as detailed in paragraph 7, Table 1. |
|
c. |
approve the projects listed in Appendix B remain in the capital programme.
|
Reason: |
To provide Members with an in-year projection in 2018/19 of the forecast spending (“outturn”) against the Council’s approved Capital Programme Budget, and to explain projected variations against individual projects and the Programme as a whole. |