Decision details

Wincanton Regeneration budget - Change of Scope

Decision Maker: District Executive

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

 

RESOLVED:

That District Executive recommend that the Chief Executive agree:-

 

a.

Option 2

  1. To allocate the full £260,000 requested from the capital contingency budget to the Wincanton Regeneration Scheme.

 

Reason:

To agree revisions to the scope of the Wincanton Regeneration project and related changes to budget including a request for additional funds from the corporate capital contingency for the project. This follows receipt of tenders for the public realm scheme.  The approach will ensure a focus on the two priorities of delivering the public realm and building repair grants (property project) during the remaining months of the project.

 

Publication date: 08/07/2022

Date of decision: 07/07/2022

Decided at meeting: 07/07/2022 - District Executive