Agenda and minutes
Venue: Virtual Meeting using Zoom meeting software. View directions
Contact: Becky Sanders, Case Officer - 01935 462596 Email: becky.sanders@southsomerset.gov.uk
Note: Start time to be confirmed.
No. | Item | ||
---|---|---|---|
To approve as a correct record the minutes of the previous meeting held on 14 May 2020. Minutes: It was noted there was a spelling mistake in the second paragraph of minute 59.
Subject to the correction being made to minute 59, the minutes of the previous meeting held on 14 May 2020 were approved as a correct record, and would be signed by the Chairman. |
|||
Apologies for absence Minutes: Apologies for absence were received from Councillors Dave Bulmer and Malcolm Cavill. |
|||
Declarations of Interest In accordance with the Council's current Code of Conduct (as amended 26 February 2015), which includes all the provisions relating to Disclosable Pecuniary Interests (DPI), personal and prejudicial interests, Members are asked to declare any DPI and also any personal interests (and whether or not such personal interests are also "prejudicial") in relation to any matter on the agenda for this meeting. Minutes: There were no declarations of interest. |
|||
Public question time Minutes: No members of public were present at the meeting. |
|||
Date of next meeting Minutes: Members noted the next meeting of the Audit Committee was scheduled for 10.00am on 30 July 2020 and would be held as a virtual meeting using Zoom. |
|||
Internal Audit Outturn Report 2019/20 PDF 81 KB Additional documents: Minutes: The Assistant Director (South West Audit Partnership) presented the report which updated members on the Internal Audit Plan 2019-20 Outturn and brought to members attention any significant findings identified through the auditing work. He highlighted some elements of the report including: · Audit areas given partial assurances. · Key corporate risks · Changes to the Audit Plan and rescheduled audits – Wide Area Network review not completed during 2019/20. · Audit Plan for 2020/21 will be constantly reviewed · Summary of significant findings and further detail of some of the issues.
During discussion, several members raised their concerns and suggestions, some of which included: · Four partial assurances with one of high importance is a significant concern and risk to reputation of the Council. · There is a common theme running through the partials – lack of training and management. · Members reflected they felt when Audit Committee was previously held monthly there was more opportunity for officers to provide frequent updates about what was being done to remediate a partial assurance. Waiting six months for an update is too long. · Some of the issues may not be the responsibility of a single person. · The Audit Committee has a responsibility to monitor, challenge and seek assurances. Many of the partials have cross cutting responsibilities and likely little to be gained by trying to hold a single person to account. · There is merit in a having regular updates on a particular action rather than a full report. · Without an explanation regarding the start of the impact from Covid – it reads as a poor report. Many points in the report would have been known before the Covid restrictions.
The Director (Support Services) noted she would be happy to take the comments made back and discuss with the Director (Service Delivery) as the partials were all within her directorate. She acknowledged the comments made, and explained that the Covid situation was having a huge impact on teams. Management were monitoring workloads and performance but the Covid situation would have an impact on response times for the issues raised.
The Assistant Director (SWAP) responded to points of detail raised during discussion including: Clarification that part of the Audit Committee’s role is the tracking and monitoring of Audit recommendations, and he could look to bring forward an update report to the committee. · There had been some delay in quarterly reporting due to Covid and pressures on staff. No reason why he could not now engage with officers for an update.
The Chairman confirmed that a regular agenda item was needed for monitoring the recommendations of audits (SWAP), which was agreed by members. At the end of discussion, the majority of members were content to note the report. One member was uncomfortable agreeing with the report as the outcomes of some audits were not as would have expected.
(Voting: 6 in favour, 1 against)
|
|||
Internal Audit Annual Report and Opinion 2019/20 PDF 64 KB Additional documents: Minutes: The Assistant Director (South West Audit Partnership) presented the report which provided an update on the position of the Internal Audit Plan at the end of 2019/20 and also provided Internal Audit’s overall ‘Opinion’ on the systems of internal control at SSDC. He highlighted key points in the report and highlighted the breakdown of priority recommendations and actions as detailed in appendix B, and also noted that adverse opinions had already been reported to the committee previously. He reminded members that part of the committee’s role was to track and monitor the audit recommendations, and to be satisfied that actions had been implemented and issues rectified.
He referred to the SWAP Performance section of the report, and noted that SWAP were required to be independently assessed at least every five years to confirm conformance to the required standards (International Professional Practices Framework). An assessment had been recently completed and confirmed that SWAP ‘Generally Conform’. He noted that he would like to bring a report forward to the committee about actions required following the assessment.
In response to points of detail raised during a short discussion, the Assistant Director (SWAP) noted that: · The audit of the auditors had been finalised in May. SWAP were now looking at how best to share the information with Members, and a report would be scheduled for committee in the near future. · Historically the opinions for SSDC were generally reasonable assurance with some partials. There had been some issues but these had been addressed. · SSDC had gone through significant change and there will be a significant impact due to Covid in the 2020/21 year. · Actions regarding Opium Power had been reported previously, but he would be happy to respond to detailed questions from members by email.
At the end of discussion, members agreed to note the report.
|
|||
2019/20 Treasury Management Activity Report PDF 576 KB Additional documents: Minutes: The Specialist (Finance) presented the report which reviewed treasury management activity and the performance against the Prudential Indicators for the 2019/20 financial year and in accordance with the Council’s Treasury Strategy, Annual Investment Policy and Treasury Management Practices. He noted most of the year had gone well, but then at the end of the financial year the situation with the Covid pandemic had had a significant impact on the investments – pooled fund investments had gone down, and borrowing had gone up. He drew attention to key elements of the report including paragraphs 8, 14, 15, 20, 22, 32, 35, 36 and 40.
During a short discussion the Specialist (Finance) and Director (Support Services) responded to points of detail, and some of their comments included: · No contingency or scenario planning had been undertaken to date regarding the possibility of negative interest rates. The concern would be raised with Arlingclose, the Council’s treasury advisors. · SSDC needs to be in each of the pooled funds for three to five years. If money withdrawn now would lose approximately £2.2m, but the average return since 2013 had been over 5%. Indications were the value of investments were starting to recover. · The Minimum Revenue Provision (MRP) was carefully monitored, and funds were allocated to an MRP account.
At the end of discussion, members unanimously agree to note the recommendations detailed in the agenda report and to recommend the Treasury Management Activity Report to full Council.
|
|||
Audit Committee Forward Plan PDF 65 KB Additional documents: Minutes: The Chairman noted two items would be added to the Forward Plan as had been discussed earlier on the agenda: · A report / summary on the audit assessment of the South West Audit Partnership (SWAP) – possibly for July. · Monitoring the recommendations of SWAP following audits – this would probably require discussion with management and therefore would be with a date to be confirmed.
Members were content to note the Forward Plan subject to the additional two reports being added as advised by the Chairman.
|