Tolbury Mill Hall, Bruton - Update on SSDC's Contribution towards the roof replacement project
10/02/2017 - Tolbury Mill Hall, Bruton
RESOLVED: that members;
(1) Noted that a Business Plan is being drawn up with assistance from SCC. This will include a sum set aside annually for further repairs & renewals on this building to protect the asset in the long-term.
(2) Agreed to ring-fence the £1786.10 underspend for a period of up to three yearsto form a sinking fund to be paid to Community Kids, to be released on receipt of an acceptable Business Plan from the charity.
Reason: to update members on the progress of the project and SSC contribution towards roof replacement at Tolbury Mill Hall, Bruton
(Voting: unanimous)
(Councillor Tony Capozzoli was absent during discussion of this item)